ATELIERSTUDIO ARH

MODERNISATION FUND

A solar investment.
A lasting impact.

Photovoltaic panels producing solar energy — illustrative stock photographyIllustrative stock photography
Financed by the Modernisation Fund

Construction of a photovoltaic power plant, fencing, utility connections and construction site organisation

ATELIER STUDIO ARH SRL signed financing agreement no. 1507/21.03.2026 for implementation of the project under Key Programme 1: Renewable energy sources and energy storage, call PFM/322/PFM_P1/NA.

Șomcuta Mare, Maramureș
Project documents

01 / Project objective

Project objective

Developing the company by increasing electricity production from renewable sources through new solar generation capacity. The project contributes to the objectives of Romania’s Integrated National Energy and Climate Plan and the Modernisation Fund.

The investment covers the photovoltaic power plant, fencing and electrical installations needed to connect it to the electricity transmission and distribution network.

Investment components

Photovoltaic power plant

Planned solar electricity generation capacity: 4.9 MW.

Șomcuta Mare, Maramureș

Fencing and site organisation

Works associated with delivering the investment.

Șomcuta Mare, Maramureș

Utility connections and grid connection

Electrical installations for connection to the electricity network.

Șomcuta Mare, Maramureș

02 / Investment structure

Investment structure

Total project value27,505,061.79RON
Maximum financing from the Modernisation Fund4,382,040.60RON
Beneficiary contribution23,123,021.19RON

Maximum financing from the Modernisation Fund represents 40% of eligible expenditure and approximately 15.93% of the total project value.

03 / Clear objectives. Measurable results.

Clear objectives. Measurable results.

The indicators below are project targets, not results already achieved.

01New installed capacity4.900 MWFMS04
02Average annual production5,576.200 MWh / yearFMS06
03Estimated annual emissions reduction3,412.060 t CO₂ / yearFMS05
04Capacity factor12.990 %FMS09
05Total production during the reference period111,524.000 MWhFMS07

04 / Project activities

Project activities

01

Preparation and procurement

Preparation of tender documents and delivery of contract award procedures.

02

Execution and monitoring

Execution and monitoring of the contracts required to implement the investment.

03

Management and audit

Project coordination and the associated financial audit.

04

Information and publicity

Implementation of the communication measures required by the financing agreement.

About the Modernisation Fund

Questions about the project?

For comments or questions about project implementation, contact us by phone or use the contact form.

LET’S KEEP IN TOUCH

Have questions?
Contact us.

Contact us